Project Supervision and Rescue Provision

Client: National Grid
Location: LNG Grain - Jetty 10 (River Medway)
Duration: 5 Days

Project: Access and Rescue Solutions were contracted by National Grid to manage the access and control of personnel during a high risk, not previously undertaken project. Working alongside contractors from across Europe, our supervisor oversaw the replacement and servicing of ESD Valves utilising Cryogenic bags as isolations from Liquid Nitrogen Gas. 

Along with the supervisor role, our ERT team were on standby, comprising of one of our Paramedics throughout the complete project ensuring an immediate response to any incident. Following months of planning, logistic management and pre-work briefings, the project was completed 24hours ahead of schedule and incident free.